At the 2004 Qidong City Comprehensive Commendation Conference, our company won another honor: the city's top 30 industrial enterprises, the ranking rose from 15 last year to 8th this year. The city's top 20 tax payers. The ranking rose from 12 industrial enterprises last year to 7th industrial enterprises this year. The city's scientific and technological progress advanced enterprises. City double civilization enterprise. Chairman Comrade Wu Jianxin was awarded the title of excellent entrepreneur in the city (won a silver medal).

In October 2004, Comrade Du Weihao, an employee of our company, won the first prize for lathe workers in Qidong City. Comrade Wang Jiandong won the first prize of fitter. Yuan Xinbing and Gu Zhengbing won the second prize of fitter. Comrade Wang Yonghua won the third prize for fitter.

After the examination and evaluation organized by the Department of Labor and Social Security of Jiangsu Province and submitted to the Ministry of Labor and Social Security for approval, Comrade Lu Pingao of our company was awarded a senior technician.

After the examination and evaluation organized by the Jiangsu Provincial Department of Labor and Social Security, our company's comrades Zhang Weidong and Ding Songping were awarded the title of technician.

On July 11, 2004, at the National Machinery Industry 500 Statistics Conference, our company was identified as the top 20 valve industry (sales revenue ranked fifth in the national valve industry).

In August 2004, the nuclear power ball valve was awarded the second prize of scientific and technological progress by Nantong Municipal People's government.

In August 2004, our company was awarded the honorary title of the most innovative industrial enterprise in Qidong City by the Qidong Municipal Party Committee and the Municipal Government.

In August 2004 by our company to implement the national key new products "loaded nuclear power ball valve", received financial support of 200000 yuan.

With the approval of Jiangsu Provincial Local Taxation Bureau, the domestic equipment of more than 500 million yuan purchased by our company in 2003 can be credited against enterprise income tax.

In order to improve the product level of the enterprise and enhance the competitiveness of the enterprise, our company has completed the transformation of a foreign joint venture, with foreign investors holding 25% of the shares. Chairman Wu Jianxin requires the company to take this as a new starting point, with high standards and strict requirements, to manufacture first-class products, create first-class talents, create first-class enterprises, and strive for the top three in the national valve industry in terms of sales revenue this year.

In April 2004, our company implemented the project number 2002EH040468 of the national torch plan "quick cut-off valve" through the acceptance of the expert group, was highly appraised by the expert group.

In April 2004, experts from the "401" Research Institute conducted a start-up inspection of the nuclear-grade butterfly and ball valves used in the main process system of the experimental fast reactor of the China Atomic Energy Research Institute, and the results were satisfactory.

In April 2004, Shanghai Nuclear Engineering Research and Design Institute and Shanghai Nuclear Power Equipment Company organized a group of experts to our company conducted research, the two sides reached a consensus on the cooperation in the development of millions of units of nuclear-grade valves.

In April 2004, three patents declared by our company, such as "vibration and noise reduction regulating valve group" (for blast furnace gas system), "nuclear power air duct isolation valve" (for nuclear power plant containment isolation system), and "special fast reversing valve for regenerative heating furnace", have been accepted by the Chinese Patent Office.

In the first quarter of 2003, Qidong industrial enterprises actually paid taxes (local taxes). On the ranking list, our company ranked second in the city.

The 2500m3 blast furnace TRT system of Shanggang No.1 Plant, which was contracted by Shaangu, was officially put into operation on March 20, 2003. The complete set of valves provided by our company is running well, and the users are satisfied!

The 120-ton converter project of Shaoguan Iron and Steel Company was successfully tested on March 22, 2003. The water seal check valve, bypass valve, three-way valve and other complete sets of valves provided by our company are in good condition!